A job-design to be time-studied has fatigue and delay allowance o

A job-design to be time-studied has fatigue and delay allowance o
| A job-design to be time-studied has fatigue and delay allowance of 10 minutes & 25 minutes per 8-hour shift. In addition 25 minutes personal time is permitted in a shift. Then, the total allowance factor necessary to calculate Standard Time for this activity will be _____. 

A. 1.143

B. 0.8

C. 12.0

D. None of these

Please scroll down to see the correct answer and solution guide.

Right Answer is: A

SOLUTION

Concept:

Allowance:

The allowance is the amount of time allowed for personal, fatigue, and unavoidable delays.

Total allowance = Personal allowance + Basic fatigue allowance + Other unavoidable delay allowance

Standard Time = Normal Time + Allowance Time

Standard Time = Normal time x Allowance factor

\(Allowance~ factor = \frac {Standard ~time}{Normal ~time}\)

Calculation:

Given:

Personal allowance = 25 minutes, Fatigue allowance = 10 minutes, Unavoidable delay allowance = 25 minutes, Standard time = 8 hour (shift)

Total allowance = Personal allowance + Fatigue allowance + Unavoidable delay allowance

Total allowance = 25 + 10 + 25 = 60 minutes = 1 hour

Standard Time = Normal Time +  Total Allowance

Normal time = Standard time - Total allowance = 8 - 1 = 7 hour

\(Allowance~ factor = \frac {Standard ~time}{Normal ~time}\)

\(Allowance~ factor = \frac 87 = 1.1428 = 1.143\)

 

Time study:

  • The classical approach to time study was developed by W. Taylor in 1911 and it is an accepted procedure for production analysis.
  • It is an analysis of a worker’s performance against a time standard.
  • Time studies are normally performed on short repetitive production types of tasks.

Terms related to Time study:

Cycle Time:

It is the total time required for a worker to complete one cycle of operation.

Machine Cycle time:

It is the total time for a machine to finish one complete cycle. It includes loading and unloading.

Normal Time:

The normal time for a particular employee is rated against the average job element-time. It is given by:

\(Normal\;Time = \frac{{Average\;element\;\times\;Performance\;rating}}{{100}}\)

Allowance Time:

  • It includes personal factors as well as unavoidable constraints encountered in the work situation.
  • It includes all unavoidable delays but rules out all avoidable delays.

Standard Time:

It is the time needed to complete an operation by an employee working at 100 % efficiency with unavoidable delays.

It is given by:

Standard Time = Normal Time + Allowance Time

Normal time = Observed time x Rating factor